EU regulatory register · FSR
Article 18Revocation
CELEX 32022R2560 · Read on 2026-08-22
Official text
Read from the EU Publications Office for this CELEX number. The wording stands as published; nothing here is rewritten or summarised.
1. The Commission may revoke a decision taken pursuant to Article 11(2), (3) or (4), Article 25(3), and Article 31(1), (2) or (3), and adopt a new implementing act in the form of a decision in any of the following cases where:
(a)
the undertaking to which the initial decision was addressed acts contrary to its commitments or the redressive measures imposed;
(b)
the initial decision was based on incomplete, incorrect or misleading information;
(c)
commitments or redressive measures are not effective.
That implementing act shall be adopted in accordance with the advisory procedure referred to in Article 48(2).
2. The revocation and adoption of a new decision by the Commission under paragraph 1 shall not affect the decision of the contracting authority or contracting entity awarding a contract. They shall also not affect a contract already concluded following such an award decision.
The text is quoted from the official source and is not legal advice. A national court reads the language version that binds in its jurisdiction.
Verifiable trust signals
- Six fixed blocks, one source per line
- No sentence written by a language model
- Engine version and read date on every answer
- No customer data, no documents, no advice
- Model card and audit published under the EU AI Act