When does an activity need an ICPE authorisation rather than a notification?

The regime depends on the threshold reached in the classified installations nomenclature: notification, registration or environmental authorisation. Authorisation is required for installations that present serious danger or nuisance to the protected interests, and it is granted by the prefect after an impact assessment, a hazard study and a public inquiry. Operating without the required authorisation is a criminal offence and can lead to a formal notice, a financial guarantee order or suspension of the activity.

Share this page

Source

Source
French Environment Code, Articles L. 511-1, L. 512-1 and L. 512-8