What happens if I build without a permit?

The building committee levies a sanction charge where works were carried out without permit or start clearance, and may order rectification.

What the source says

  • Chapter 11 section 51: a sanction charge is levied.
  • Chapter 10 section 3: start clearance is required before works begin.
  • Chapter 10 section 34: final clearance before the structure is used.

Source rows

  • PBL
    SFS 2010:900 · The municipal building committee, with Boverket as central authority · Retrieved 2026-08-20
  • BBR
    BFS 2011:6 med ändringar · Boverket, the Swedish National Board of Housing · Retrieved 2026-08-20

For the owner, landlord or seller

The charge applies even where a permit is later granted; apply in advance.

For the tenant, buyer or client

A buyer should check final clearance before access; it follows the property.

Next step

Read the provisions in the register and Boverket's building rules.

The page states what the source says under the stated conditions. It is not advice in an individual matter.