What happens if I build without a permit?
The building committee levies a sanction charge where works were carried out without permit or start clearance, and may order rectification.
What the source says
- Chapter 11 section 51: a sanction charge is levied.
- Chapter 10 section 3: start clearance is required before works begin.
- Chapter 10 section 34: final clearance before the structure is used.
Source rows
For the owner, landlord or seller
The charge applies even where a permit is later granted; apply in advance.
For the tenant, buyer or client
A buyer should check final clearance before access; it follows the property.
Next step
Read the provisions in the register and Boverket's building rules.
The page states what the source says under the stated conditions. It is not advice in an individual matter.
Next step
Three ways to put the register to work in your own practice.
Start with your task
Litigation
Find support in a judgment
Search guiding decisions, see what became final and follow changes in the law.
In-house, deals
Map the rules in a transaction
Move from theme to act and on to the article that carries the duty.
Compliance
Assess the risk in a process
Risk scoring per legal area, with the sources behind every score.