What applies to delay in a consumer construction contract?

On delay the consumer may withhold payment, require performance and claim damages, and rescind where the delay is material. For house construction a statutory penalty also applies under the delay rules.

What the source says

  • Section 24 of the Consumer Services Act: the consumer may withhold payment and require performance on delay.
  • Section 29: rescission where the delay is of material importance.
  • Section 31: damages for delay unless the trader shows an impediment beyond its control.

Source rows

  • Konsumenttjänstlagen
    SFS 1985:716 · The Consumer Agency, with the National Board for Consumer Disputes reviewing claims · Retrieved 2026-08-20

For the owner, landlord or seller

Document impediments continuously, the control test looks at what was foreseeable at contracting.

For the tenant, buyer or client

Complain about the delay in writing and state the time you require, that anchors the remedies.

Next step

Read delay together with the defect rules, the same works are often tested on both.