EU-domstolen · Dom

C-24/19A and Others v Gewestelijke stedenbouwkundige ambtenaar van het departement Ruimte Vlaanderen, afdeling Oost-Vlaanderen

Avgjort
2020-06-25
ECLI
ECLI:EU:C:2020:503
CELEX
62019CJ0024
Rettskraft
Endelig, avgjørelsen kan ikke ankes

Domstolens egne nøkkelord

Reference for a preliminary ruling — Directive 2001/42/EC — Environmental impact assessment — Development consent for the installation of wind turbines — Article 2(a) — Concept of ‘plans and programmes’ — Conditions for granting consent laid down by an order and a circular — Article 3(2)(a) — National instruments setting the framework for future development consent of projects — Absence of environmental assessment — Maintenance of the effects of national instruments, and consents granted on the basis of those instruments, after those instruments have been declared not to comply with EU law — Conditions.

Tolker

    Lest hos EU:s publikationsbyrå, Cellar (EUR-Lex och CURIA) den 2026-08-22.

    Raden gjengir det kilden skriver. Den er ikke et referat, ikke en konklusjon om en enkelt sak og ikke juridisk rådgivning.

    Kontrollerbare tillitssignaler

    • Seks faste blokker, én kilde per linje
    • Ingen setning skrevet av en språkmodell
    • Motorversjon og lesedato på hvert svar
    • Ingen kundedata, ingen dokumenter, ingen rådgivning
    • Modellkort og revisjon publisert etter AI-forordningen

    ModellkortRevisjon